Commissioners Court Meeting


Issue viewing agenda items? Click here to switch to the old format.

Print

Return to the Search Page Return to the Agenda
 
Meeting Date: 06/26/2023  
APPROVAL OF CHANGE ORDER NO 2 FOR THE SHERIFF REMODELING PROJECT
Submitted for: Martha Palacios Submitted By: Martha Palacios
Department: Engineering  

Subject:
Discussion and possible action to approve Change Order No. 2 in the amount of $381,449.25 to Summit Building & Design for the Webb County Sheriff's Administration Office Remodeling Project; and have the County Judge sign any relevant documents and any other matters incident thereto. [Account #3905-7230-001-474501-002 (Construction In Progress-Finish Out / Remodeling)]

Issue: Installation is needed for future generator connections.

Solution: Extend 8 runs of 4" conduits to feed Automatic Transfer Switch, install a 7'x4'x2' box for splice connections, feeders from main disconnect to transfer switch and from transfer switch to main switch board.

Result: Ratify approval of change order to continue and finish with project modifications.
Background:
N/A
Previous Court Action:
N/A

Fiscal Impact
Budget Account Number: 0
Funding Source: 0
Balance: 0
Financial Impact:
Account No. 3905-7230-001-474501-002 (Construction In Progress-Finish Out / Remodeling)
Attachments
CHANGE ORDER NO. 2


    