APPROVE CLOSEOUT AND PAY RETAINAGE OF CSCD/PAL BUILDING
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve closeout and release of retainage to Davila Construction, Inc., in the amount of $49,978.29 for the completion of the Community Supervision and Corrections Department/Police Athletic League on Hwy 83S Project (CSCD/PAL).
[Account #742-2311]
Issue:
Project closeout.
Solution:
Approve closeout and payment of retainage.
Result:
Project completion.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
Account #742-2311
Attachments
PAY APPLICATION #13