APPROVE CHANGE ORDER NO. 1-RFP 2015-07 UTILITIES WAREHOUSE
Submitted for: Martha Palacios Submitted By: Martha Palacios
Department: Engineering  

Subject:
Discussion and possible action to approve Change Order No. 1 in the amount of $12,325.00 to AZAR Services, L.L.C., for 1,750 square feet  of 6" reinforced concrete slabs under two canopies and 4 feet wide sidewalks for the new Utilities Warehouse. [Account #745-3001-8801-7 (Capital Outlay Water Utilities)]

Issue: Additional work area is needed to work on equipment.

Solution: Add concrete slabs under canopy area.

Result: Double the work area.
Background:
N/A
Previous Court Action:
N/A

Fiscal Impact
Budget Account Number: 0
Funding Source: 0
Balance: 0
Financial Impact:
Account #745-3001-8801-7 (Capital Outlay Water Utilities)
Attachments
CHANGE ORDER
CHANGE ORDER DRAWING


    