APPROVE CLOSEOUT AND FINAL PAYMENT TO AZAR FOR WATER UTILITIES WAREHOUSE COMPLETION
Submitted for: Martha Palacios Submitted By: Martha Palacios
Department: Engineering  

Subject:
Discussion and possible action to approve closeout and final payment in the amount of $17,653.50 and release retainage in the amount of $15,916.96 for a total amount of $33,570.46 to Azar Services, LLC., for the completion of RFP 2015-07 Water Utilities Warehouse (P.O. 16-0009095).  [Account #745-3001-8801-7 (Capital Outlay Water Utilities) and Account #745-2311 (Retainage Account)]

Issue: 
Closeout project after completion.

Solution: Approve and pay retainage.
 
Result: 
Project Completed.
 
Background:

Account #745-3001-8801-7 (Capital Outlay Water Utilities & Account 745-2311 (Retainage Payable)

Previous Court Action:
  1. Project RFP 2015-07 approved July 25, 2016
  2. Change Order approved January 9, 2017

Fiscal Impact
Budget Account Number: 0
Funding Source: 0
Balance: 0
Financial Impact:

Account #745-3001-8801-7 (Capital Outlay Water Utilities & Account 745-2311 (Retainage Payable)

Attachments