Release Retainage on Botines Fire Station
Submitted for: Nathan Bratton Submitted By: Nathan Bratton
Department: Civil Legal Division  

Subject:
Discussion and possible action to release approximately $75,226.00 in retainage to HydroWorks and it's subcontractors and material suppliers for work completed and materials integrated into the project and accepted on the Botines Fire Station and any matters incident thereto. [Account #3150-206000 (Retainage Payable)]
Background:
10% retainage was withheld by County as required by law for the benefit of any unpaid subcontractors and material suppliers.  Substantial Completion of the facility was issued on Octobder 30, 2018.
Previous Court Action:

Fiscal Impact
Budget Account Number: 3150-206000
Funding Source: Retainage Account
Balance: $75226.00
Financial Impact:
The retainage is 10% of the completed work and integrated material and supplies from the construction of the Botines Fire Station.

    