Commissioners Court Meeting
Issue viewing agenda items? Click here to switch to the old format.
Print
Return to the Search Page
Return to the Agenda
Meeting Date:
12/09/2019
APPROVAL OF CHANGE ORDER FOR THE YOUTH VILLAGE
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve Change Order #1 in the amount of $386,727.90 to Summit Building & Design for the Webb County Youth Village Rehabilitation Center Project. All the items included are considered upgrades with the exception of the drive loop wide-outs, which are being requested by the Fire Department prior to permitting; and authorize the Webb County Judge to execute all relevant documents; and any other matters incident thereto.
[Accounts #3115-2450-001-470000 (Capital Outlay), #3140-2450-001-470000-030 (Capital Outlay-Construction), Interest Income Series 2006 and 2013, and #1001-1130-001-431007-010 (Operational Reserve)]
Issue:
Additional project improvements shall be completed as detailed in the Change Order. All labor, materials and equipment shall be included.
Addition of (72) parking spaces.
Addition of back-up power supply (generator)
Loop driveway wide-outs (as required by the Laredo Fire Department) due to changes in Fire Code.
LED fixture upgrades.
Addition of Erosion Control Blankets.
Acquiring additional easement for electric utility infrastructure.
Solution:
Approve Change Order #1 and proceed with the additional project improvements.
Result
: Project will be completed as detailed under the proposed Change Order.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
Account #3115-2450-001-470000 (Capital Outlay) & #3140-2450-001-470000-030 (Capital Outlay-Construction)
Attachments
CHANGE ORDER DOCUMENT
AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.