Meeting Date: 09/13/2021  
Wastewater Treatment Plant Blowers
Submitted for: Tom Sanchez Submitted By: Tom Sanchez
Department: Water Utilities  

Subject:
Discussion and possible action to approve the purchase of Two (2) additional Blowers at a cost of $37,850.00 not to exceed $75,700.00 from Laredo Machine Shop, Rio Bravo, Texas. [Account #7220-7270-001-474501 (Water Utility Improvement Series 2016, Construction In Progress-Wastewater)]

Issue: Wastewater Blowers are used to supply the needed oxygen to the Wastewater Treatment Process, when this supply of air is stopped, adequate treatment will no longer be reached.

Solution: Purchase and replacement of equipment.

Result: Operational flexiblity and State Regularoty compliance.
Background:
N/A
Previous Court Action:

Fiscal Impact
Budget Account Number: 0
Funding Source: 0
Balance: 0
Financial Impact:
7220-7270-001 - Water Utility Improvement Series 2016
Attachments
Wastewater Treatment Plant Blowers
Wastewater Treatment Blower Manual


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.