10/08/2021
Mirando Water Well Project No. 7219095 change order #2
Submitted for:
Alexandra Castaneda
Submitted By:
Alexandra Castaneda
Department:
Water Utilities
Subject:
Discussion and possible action to approve
change order No. 2
in the amount of $10,160.00 and a time extension for the date of October 30, 2021 to the contract with RG Enterprises, LLC, due to difficult soil for the Texas Department of Agriculture TXCDBG Mirando Water Well Phase 1 Project No. 7219095; with further approval to transfer funds required from account #3523-1150-001-410000; and authorizing the County Judge to execute any relevant documents; and any other matters incident thereto.
[Requested by James Flores, Economic Development Director; Account #3523-7230-001-432001 (Construction in Progress)]
Issue:
The contractor has been hitting rock and caliche that has been damaging their equipment and slowing down the process considerably.
Solution:
Approve change order that will allow for the contractor to complete contractual activities and a time extension until October 30, 2021.
Result:
Contractor will finish construction within contract timeframe.
Background:
N/A
Previous Court Action:
Fiscal Impact
Budget Account Number:
unkn
Funding Source:
TDA Colonia Fund Con
Balance:
unkn
Financial Impact:
N/A
AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.