Commissioners Court Meeting
Issue viewing agenda items? Click here to switch to the old format.
Print
Return to the Minutes Page
Meeting Date:
01/08/2024
APPROVAL OF CHANGE ORDER FOR THE QUAD CITY FIRE STATION AND JP. 3 RENOVATION PROJECT
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve Change Order No. 1 for Muralla Construction LLC., for the Quad City Fire Station and Justice of the Peace Pct. 3 Expansion Project for an additional 79 calendar days. There will be no impact to the account and have the County Judge sign any relevant documents and; any other matters incident thereto.
[No Impact to Account]
The Original Contract (Contract Sum) price is:
$801,300.00
The next change by previous authorized change orders:
$0
The Contract (Contract Sum) prior to this change order was:
$801,300.00
The Contract (Contract Sum) will be (increased) (unchanged) by this change order in the amount of:
$0
The New Contract (Contact Sum) including this change order will be:
$801,300.00
The Contract Time will be increased by:
79 days
The date of Substantial Completion as of the date of this change order therefore is:
February 9, 2024
Issue:
Requesting additional days due to lead time of approved submittal items; Chlorination system, Water Tank, Fiber Glass Enclosure, Electrical Panel Board and Breakers. Equipment Lead Time to deliver will be eight (8) weeks and an additional two (2) weeks for installation.
Solution:
Approval of change order by Commissioner Court.
Result:
Approval of change order will continue and finish with project modifications.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
No Impact to the Account
Attachments
CHANGE ORDER NO. 1
PURCHASE ORDER
AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.