Meeting Date: 10/23/2023  
Release of withheld retainage payment to Schindler Elevator
Submitted for: Yolanda Iruegas Submitted By: Yolanda Iruegas
Department: Building Maintenance  

Subject:
Discussion and possible action to approve the release of the withheld partial retainage payment in the amount of $5,838.73 from the original invoice amount of $116,761.00 payable to Schindler Elevator Corporation Invoice #7401594696 and authorize the County Judge to execute all relevant documents; and any other matters incident thereto. [Account #3868-7230-001-443000-260 Repairs & Maintenance Webb County Building (formerly Webb County Title Building) and Account #3868-206000 (Elevator Repairs 2019A Retainage Payable)]

Issue: Elevator improvement was completed as detailed under contract specifications.

Solution: Commissioners Court authorizes the release of retainer fee for the modernization of the Webb County Title Building elevator.

Result: Schindler Elevator Corporation will be paid for services rendered.
Background:
N/A
Previous Court Action:
Commissioners Court awarded Schindler Elevator the modernization and preventive maintenance project for all County elevators on June 24, 2019, item 30.

Fiscal Impact
Budget Account Number: N/A
Funding Source: N/A
Balance: N/A
Financial Impact:
None

    