Commissioners Court Meeting
Issue viewing agenda items? Click here to switch to the old format.
Print
Return to the Minutes Page
30.
Meeting Date:
11/10/2014
CLOSE OUT AND ACCEPTANCE OF ROOF REPLACEMENT PROJECT
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios, Engineering
Department:
Engineering
Subject:
Discussion and possible action to approve the closeout and acceptance of the Webb County Building Roof Replacement Project (4101 Juarez) and the release of the 10% of retainage in the amount of $21,037.00 to Aftermath Roofing Construction & Renovations, Inc.
[Account #739-1200-8801-14]
Background:
Project approved August 11, 2014 - Item No. 21.
Previous Court Action:
N/A
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
739-1200-8801-14
Attachments
RETAINAGE INVOICE
AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.