CSCD 83 SOUTH-REMODELING CHANGE ORDER NO. 1
Submitted for: Martha Palacios Submitted By: Martha Palacios, Engineering
Department: Engineering  

Subject:
Discussion and possible action to approve Change Order #1 for the C.S.C.D. Remodeling Project located on Hwy 83 South to Davila Construction in the amount of $199,565.86. Increasing the contract amount to $999,565.85. [Fund #742]
Background:
Contractor will increase their current contract of $800,000.00 by almost 25% for the installation of a new HVAC system for $145,146.82 and new lighting system for $54,419.04
Previous Court Action:
Awarding of the C.S.C.D. remodeling contract on March 24, 2014.

Fiscal Impact
Budget Account Number: 0
Funding Source: 0
Balance: 0
Financial Impact:
Fund #742