Commissioners Court Meeting
Issue viewing agenda items? Click here to switch to the old format.
Print
Return to the Minutes Page
49.
Meeting Date:
11/09/2015
CSCD BUILDING - SIMPLEXGRINNELL
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve a correction to the funding for the Fire Protection System installation for the Community Supervision & Corrections Department/Police Athletic League (C.S.C.D./PAL) renovation on Hwy 83S, Purchase Order No. 15-0002814 (SIMPLEXGRINNEL). This correction was a result of a misinterpretation of the vendor's reduction quote document. An increase of $37,971.70 is needed to the current amount of $42,860.37 on Purchase Order No.15-0002814 (SIMPLEXGRINNEL).
[Account #742-8001-12 (Rebuild Restitution Center-Series 2013)]
Issue:
Vendor's reduction quote document for the connection to the main and underground piping for fire protection was reduced too much due to quote being misinterpreted.
Solution:
Increase Purchase Order No. 15-0002814 (SIMPLEXGRINNELL) by $37,971.70
Result:
Vendor can be paid for work done.
Background:
Commissioner Court dated September 14, 2015 Agenda Item #60 - SimplexGrinnell Fire Protection System contract was reduced from $97,046.30 to $42,860.37.
Previous Court Action:
On Commissioner Court on September 14, 2015, Purchase Order No. 15-0002814 (SIMPLEXGRINNEL) was reduced by $54,185.93
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
Account #742-8001-8801-12