Commissioners Court Meeting


Issue viewing agenda items? Click here to switch to the old format.

Print

Return to the Minutes Page
  32.       
Meeting Date: 02/09/2015  
Fire Protection System for the CSCD/PAL Building
Submitted for: Martha Palacios Submitted By: Martha Palacios, Engineering
Department: Engineering  

Subject:
Discussion and possible action to amend the contract with TYCO SimplexGrinnell for the "Fire Protection System” for the Community Supervision & Corrections Department/Police Athletic League (C.S.C.D./PAL).  [Account #742-8001-8801-12  (Capital Outlay Renovations)]    
 
Problem:  The original contract for the renovation of the C.S.C.D./PAL building did not include the completion of the fire protection system requirements set by City Ordinance to meet code. TYCO SimplexGrinnell was selected through the Texas State (on contract) to provide services at $55,296.30 and Commissioners Court approved the item on January 12, 2015. After reevaluation of the costs by the Engineering Department, it was identified that the total cost would be for $97,046.30.
 
Solution:  Amend contract with TYCO SimplexGrinnell for the Fire Protection System.
 
Result:  Comply with City of Laredo Building Fire Protection System installation services.
Background:
An Agenda Line Item Transfer has been submitted for next Commissioner Court meeting dated February 9, 2015 for Account 742-8001-8801-12 Capital Outlay Renovations - amount of $41,750.00.
Previous Court Action:
N/A

Fiscal Impact
Budget Account Number: 0
Funding Source: 0
Balance: 0
Financial Impact:
Account # 742-8001-8801-12
Attachments
QUOTE


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.