Meeting Date: 02/13/2017  
Spiral Screen Electrical Panel Instalation
Submitted for: Adrian Montemayor Submitted By: Adrian Montemayor
Department: Engineering  

Subject:
Discussion with possible action to approve the award of project to Square E Engineering, lowest proposal cost of $23,970.00, for the installation of a new electrical panel for the Spiral operating primary screen at the Webb County Wastewater Treatment Plant in Rio Bravo, Texas. This is to include all materials, labor, initiating, and training. Project is listed as approved onto 2017 Capital Outlay projects. [Account #758-8005-8601 (2016 Bond Series)]

Issue: Installed equipment for screen continue to malfunction due to inconsistent electrical power due to old electrical panel.

Solution: Authorize issuance of purchase order to lowest & responsible bidder.

Result: Complete installation and operation of screen consistently.
Background:
None
Previous Court Action:
None

Fiscal Impact
Budget Account Number: 758 2016 Bond Series
Funding Source: 8006 Wastewater
Balance: NA
Financial Impact:
8601- Construction in Progress

    