  28.       
Meeting Date: 03/29/2016  
APPROVE SUPPLEMENTAL WORK AUTHORIZATION NO. 1 TO WORK AUTHORIZATION NO. 1,2&3
Submitted for: Martha Palacios Submitted By: Martha Palacios
Department: Engineering  

Subject:
Discussion and possible action to approve Supplemental Work Authorization No. 1 to Work Authorization No. 1, No. 2 and No. 3 of the contract between Webb County and S&B Infrastructure to extend the Work Authorization duration to 36 months with a new termination date of September 22, 2017 for services being performed for the Espejo-Gates Projects under the County Transportation Infrastructure Fund (CTIF)

Issue: Final Plans, Specifications and Estimates for the Espejo-Gates Bridge #1, #2 and Roadway have not been completed due to unforeseen delays in the projects. Specifically, difficulties with obtaining access to the surrounding private property made it difficult to complete necessary surveying activities.

Solution: Extend the initial duration of Work Authorization No. 1 (Bridge #1), No. 2 (Bridge #2) and No. 3 (Roadway).

Result: Provide adequate time for the completion of services to include:  Final Plans, Specifications and estimates; construction bidding; construction management and support; and project administration.
Background:
N/A
Previous Court Action:
N/A

Fiscal Impact
Budget Account Number: 0
Funding Source: 0
Balance: 0
Financial Impact:
N/A
Attachments
No. 1
No. 2
No. 3
RESOLUTION
ADVANCE FUNDING AGREEMENT


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.