Award ITB 2022-010 Casa Blanca Golf Course Improvements-Romo Contractors
Submitted for: Joe Lopez Submitted By: Joe Lopez
Department: Purchasing  

Subject:
Discussion and possible action to award Invitation to Bid (ITB) 2022-010 “Casa Blanca Golf Course Improvements” to the lowest and responsible bidder Romo Contractors, LLC and select Alternates in accordance with the Texas Government Code, Section 2269.101, Contracts For Facilities: Competitive Bidding and to further authorize a budget amendment from the General Operational Reserve Account for amounts exceeding $213,075.00 and any other matters incident thereto. [Account#7100-7230-001-470000 (Casa Blanca Golf Course Construction in Progress-Capital Outlay)]
 
  Architects Opinion of Probable Cost  Lowest Bid 
Base Bid:
Includes:
Demolition, Concrete Patio Area,
Site Electrical, Palapa Foundation,
Palapa Wood Framing, Palapa Stucco Finish,
Palapa Roof & Soffit, Palapa Electrical,
General & Misc. Requirements,
Contractor OH & Profit Allowance 







$254,844.85







$263,900.00
Alternate No. 1
Includes:
Stage Area, Wood Arbor, Bar Millwork,
Palapa Plumbing
Contractor OH & Profit




$78,228.60




$78,000.00
Alternate No. 2:
Includes:
Ceiling Fans, Overhead Coiling Doors,
Contractor OH & Profit



$51,092.00



$95,500.00
Grand Total $384,165.45 $437,400.00
 
Commissioners Court has the authority to award the contract to the responsible bidder who submits the lowest and best bid or reject all bids and publish a new notice.  Local Government Code § 262.027, Awarding of Contract.
 


Issue: Two (2) formal bids were submitted for this formal solicitation. Bids received from two local contractors: Romo Contractors, LLC and Quantcorp Construction, LLC. Total base bid with alternates was $437,400.00 and $535,653.00 respectively.
 
Solution: Consider awarding to lowest and responsible bidder for Base Bid and Alternates and option to select Alternates.
 
Result: If awarded by Commissioners Court, construction contract preparation would be initiated by Civil Legal.
Background:
N/A
Previous Court Action:
Commissioners Court on March 14, 2022 authorized the Purchasing Agent to seek competitive bids in accordance with the Texas Government Code; Section 2269.101.
 

Fiscal Impact
Budget Account Number: 7100-7230-001-470000
Funding Source: Capital Outlay
Balance: $213,000.00
Financial Impact:
7100-7230-001-470000
Capital Outlay
$213,000.00
 
Attachments
Bid Tabulation-Casa Blanca Golf Course Improvements
Opinion of Probable Costs
Item #16 - 1 Casa Blanca Golf Course Improvements - Romo Contractor - Executed


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.