47.
Meeting Date:
05/11/2015
Rio Bravo
Submitted for:
Leticia Gutierrez
Submitted By:
Leticia Gutierrez
Department:
Purchasing
Subject:
Discussion and possible action to fund Request for Proposals 2015-04 Rio Bravo Wastewater Plant Chlorine System Replacement in the amount of $21,342.00.
[Requested by Adrian Montemayor, Water Utilities System Manager] [Approved by Capital Outlay Committee, Fund #604-0101-8103]
Issue:
Replacement and rehabilitation of existing equipment
Solution:
The replacement and rehabilitation of existing equipment will return to service the initial design of the Chlorination facilites as its original operation and provide a safe but effective dosage of the Plant's effluent discharge.
Result:
Compliance with TCEQ requirements and safe use of chlorine gas for our employees and neighbors.
Background:
n/a
Previous Court Action:
Awarded on Commissioners Court on April 13 2015 item #43 to award to Environmental Improvements Inc.
Fiscal Impact
Budget Account Number:
604-0101-8103
Funding Source:
604
Balance:
$21,342.00
Financial Impact:
21,342.00
Budget Account Number:
604-0101-8103
Funding Source:
604
Balance:
21,342.00
Financial Impact:
21,342.00