Commissioners Court Meeting
Issue viewing agenda items? Click here to switch to the old format.
Print
Return to the Minutes Page
Meeting Date:
06/24/2019
Amendment 1 to Architect Contract - Frank Architects HEB Building
Submitted for:
Nathan Bratton
Submitted By:
Nathan Bratton
Department:
Civil Legal Division
Subject:
Discussion and possible action to enter into Amendment 1 to the Standard Form of Agreement Between Owner and Architect (AIA Document B101-2017) between Webb County and Frank Architects Inc. reducing the owner's budget for the Cost of Work from Five Million Dollars ($5,000,000) to Four Million Six Hundred Four Thousand Four Hundred Dollars ($4,604,400); authorizing the County Judge to sign all relevant documents and any matters incident thereto.
Background:
The reduction in Cost of Work will bring total cost of project, including Architect fees, to 5,000,000 as budgeted
Previous Court Action:
Commissioners Court approved the Architects contract on April 8, 2019
Fiscal Impact
Budget Account Number:
CO 2019
Funding Source:
2019 CO A
Balance:
5,000,000
Financial Impact:
Reduction in Cost of Work brings cost of project into budgeted amount of $5,000,000
Attachments
Amendment 1 to AIA contract HEB Building