Raba Kistner Justice Center Roof assessment, design and const. admin
Submitted for: Nathan Bratton Submitted By: Nathan Bratton
Department: Civil Legal Division  

Subject:
Discussion and possible action to enter into an engineering contract with Raba Kistner Consultants, Inc. for the evaluation and assessment of the Justice Center Roof (14 calendar days) at a cost of Twenty-Five Thousand Two Hundred Fifteen Dollars and for remediation/repair design and construction administration services (60 calendar days) at a cost based on a sliding scale of the construction cost of between 7.5% to 8.9% and any matters incident thereto; authorizing the County Judge to sign all relevant documents. [Account #1001-1130-001-432001 (Professional Services)]

Issue: The Justice Center roof leaks during moderate or heavy rain causing damage to the ceilings and equipment in the building.

Solution: Evaluate the roof and design repairs and remediation of the roof.

Result: The County may then bid out the design and repair or remediate the roof.
Background:
Raba Kistner was selected by the Commissioners Court to evaluate and assess the roof and design repair/remediation of the roof.
Previous Court Action:

Fiscal Impact
Budget Account Number: 1001-1130-001-432001
Funding Source: Professional Service
Balance: unkn
Financial Impact:
TWENTY-FIVE THOUSAND TWO HUNDRED FIFTEEN DOLLARS ($25,215.00) for Phase I Services (?Roof Assessment?)t
Attachments
Contract Raba Kistner Justice Center Roof
Item #17 - Raba Kistner Consultants Justice center Roof - Executed


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.