Raba Kistner Justice Center Roof assessment, design and const. admin
Submitted for:
Nathan Bratton
Submitted By:
Nathan Bratton
Department:
Civil Legal Division
Subject:
Discussion and possible action to enter into an engineering contract with Raba Kistner Consultants, Inc. for the evaluation and assessment of the Justice Center Roof (14 calendar days) at a cost of Twenty-Five Thousand Two Hundred Fifteen Dollars and for remediation/repair design and construction administration services (60 calendar days) at a cost based on a sliding scale of the construction cost of between 7.5% to 8.9% and any matters incident thereto; authorizing the County Judge to sign all relevant documents.
[Account #1001-1130-001-432001 (Professional Services)]
Issue:
The Justice Center roof leaks during moderate or heavy rain causing damage to the ceilings and equipment in the building.
Solution:
Evaluate the roof and design repairs and remediation of the roof.
Result:
The County may then bid out the design and repair or remediate the roof.
Background:
Raba Kistner was selected by the Commissioners Court to evaluate and assess the roof and design repair/remediation of the roof.
Previous Court Action:
Fiscal Impact
Budget Account Number:
1001-1130-001-432001
Funding Source:
Professional Service
Balance:
unkn
Financial Impact:
TWENTY-FIVE THOUSAND TWO HUNDRED FIFTEEN DOLLARS ($25,215.00) for Phase I Services (?Roof Assessment?)t