CLOSE OUT AND RELEASE OF RETAINAGE FOR NEW FIRE STATION AND ADMINISTRATION BUILDING
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve and accept closeout and final payment in the amount of $19,573.65 (Change Order #2) and release of retainage in the amount of $24,506.94 for a total amount of $44,080.59 to Hydroworks Inc., for the completion of the New Fire Station and Administration Building.
[Accounts #3150-1020-001-470000 (Capital Outlay) & #3020-206000, #3150-206000, #3195-206000 (Retainage Payable)]
Issue:
Closeout project after completion. Change Order #2 ($19,573.65) will be paid with Purchase Order No. 2017-00001822. Retainage ($24,506.94) will be paid with Purchase Order No. 16-0004722.
Solution:
Approve and pay retainage.
Result:
Project Completed.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
Accounts #3150-1020-001-470000 (Capital Outlay) & 3020-206000, 3150-206000, 3195-206000 (Retainage Payable)
Attachments
PAY APPLICATION NO. 15
CHANGE ORDER NO. 2
PURCHASE ORDER NO. 2017-00001822