Meeting Date: 04/26/2021  
Ratification of Change Order 1 to Espejo Molina Overlay Project
Submitted for: Nathan Bratton Submitted By: Nathan Bratton
Department: Civil Legal Division  

Subject:
Discussion and possible action to ratify the execution of Change Order No. 1 to the Espejo Molina Road Overlay Project, (original contract of March 30, 2021) increasing the contract Sixty-One Thousand Five Hundred Eighty-Six Dollars ($61,586) which adds an additional 1200 linear feet of paving to the project for a total contract cost of Eight Hundred Fifty-Four Thousand Six Hundred Eighty Two Dollars and Seventy Cents ($854,682.70) and any matters incident thereto. [Funding is 2014 CTIF Capital Outlay #3720-7230-708-470000]
Background:
There was a shortfall in the original calculations for the overlay project, the additional paving takes the project all the way to the U.S. 83 frontage road.
Previous Court Action:

Fiscal Impact
Budget Account Number: 3720-7230-708-470000
Funding Source: 2014 CTIF
Balance: n/a
Financial Impact:
$61,586 change order to add additonal paving.
Attachments
Change Order No. 1 Espejo Molina
Item #7f - Espejo Molina Road Overlay - Executed


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2024 Destiny Software Inc. All Rights Reserved.