Discussion and possible action to reject all bids received for “Invitation to Bid #2020-004 Las Lomas Drainage Project” and any other matters incident thereto.
Issue: Project is 80% complete. Construction work is being completed by Webb County Road and Bridge personnel.
Solution: Reject all Bids received and authorize road and bridge department to proceed with completion of project.
Result: Final drainage and road improvements are scheduled to be completed by July 2020.
Background:
N/A
Previous Court Action:
Fiscal Impact
Budget Account Number:
3875-7230-001-474501
Funding Source:
Construction in Prog
Balance:
$7,832.00
Financial Impact:
Account: 3875-7230-001-474501 Construction in Progress
Balance: $7,832.00
Attachments
Bid Tabulations-ITB 2020-004 Las Lomas Drainage Project