Discussion and possible action to approve final payment and release of retainage in the amount $12,680.90 to Sal Construction Management for the completion of the El Cenizo Control Valve Improvements Project and authorize the County Judge to execute all relevant documents; any other matters incident thereto. [Account #7220-206000 (Retainage Payable)]
Issue: Final retainage payment to contractor in the completion of project scope in full.
Solution: Approval of payment.
Result: Issue final payment and close project.
Background:
El Cenizo Control Valve Improvement Project to meet all Texas Commission on Environmental Quality (T.C.E.Q.) statutory requirements for the Webb County/El Cenizo Water/Wastewater Treatment Plant Elevated Water Storage Tank.