APPROVAL OF AMENDMENT NO. 4 FOR PROFESSIONAL SERVICES FOR THE YOUTH VILLAGE PROJECT
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve Contract Amendment #4 (AIA Document G802-2007) in the amount of $29,000.00 to Ausland Architects and Metaform Studio for the Webb County Youth Village Rehabilitation Center Project. Amendments to the professional services contract is based on the seven and a half percent (7.5%) of the final construction cost of the Four Million Seventy-Two Thousand Nine Hundred Twenty-Seven Dollars and Ninety Cents ($4,072,927.90) as amended by Change Order No. 1, approved by Webb County Commissioner Court on December 9, 2019 to Summit Building and Design, and; authorize the Webb County Judge to execute all relevant documents; and any other matters incident thereto. [Account #3140-2450-001-470000-030 (Capital Outlay)]
Issue: Additional A/E Fees for professional design service fee as a result of Change Order #01 for the Youth Village Rehabilitation Project Program.
Solution: Approve Contract Amendment No. 04, based on 7.5% of final construction cost.
Result: Ausland Architects in Association with Metaform Studio, look forward to realizing the completion of this import project for Webb County.