Discussion and possible action to ratify, by Order, the following budget amendment (line item transfer) within Golf Course funds:
Acct. Number
Acct. Name
Adopted
Request
Current
End Bal.
From:
7100-6130-001-458000
Administrative Travel
$19,600
$1,500
$10,340.40
$,8840.40
To:
7100-6080-001-443000-155
Repairs and Maint. Irrigation
$5,000
$1,500
$3,117.41
$4,617.41
Issue: To supplement the irrigation project there are additional parts and sprinkler heads to complete the project properly. Remaining funds in the source account should be sufficient for the remainder of the fiscal year due to travel restrictions.
Solution:Transfer as requested above.
Result: There will be sufficient funds in all budget line items to pay requested items.