Correcting and approving Change orders 01-010 for the ME Remodel
Submitted for:
Nathan Bratton
Submitted By:
Nathan Bratton
Department:
Civil Legal Division
Subject:
Discussion and possible action to approve corrected change orders numbers 002 through 006 and change order 008 (previously approved September 13, 2021), with no increase or decrease in the approved amounts approving change order 007 adding 13 rain days and extending the contract to November 9, 2021 (no increase or decrease in cost) approving change order number 010 in the amount of Eight Thousand One Hundred Fifteen Dollars ($8,115.00) for the Medical Examiner Renovation Project and any matters incident thereto; authorizing the County Judge to sign all relevant documents. [Account #3871-3100-001-474501 (Construction in Progress)]
Background:
Correction of form of Change Order and approval of two change orders.