Discussion and possible action to authorize the Purchasing Agent and Budget Officer to secure a public property finance contract to fund the following capital equipment with a projected cost of $1,772,580.00 and to further return to Commissioners Court with a proposed financing plan for consideration and any other matters incident thereto.
Projected Cost for Police Equipment for 31 Units
Police Lighting for Marked & Unmarked Units
Qty. 31
Sub-Total
$545,000
Watch Guard in Car Video System / Body Cam
Qty. 18
Sub-Total
$86,000
APX 6500 Mobile Radios
Qty. 31
Sub-Total
$186,000
Police Lights / Equipment Transfers / Decals
Qty. 10
Sub-Total
$36,000
Total Projected Cost for Police Equipment:
$853,000
Projected Cost for Purchase / Install of Three (3) Emergency Generators for Fire Stations
Los Botines Fire Station
Equipment: $37,000
Installation: $15,000
Qty. 1
Sub-Total
$52,000
Main Fire Station
Equipment: $5,000
Installation: $31,000
Qty. 1
Sub-Total
$36,000
Quad City Fire Station
Equipment: $31,000
Installation $21,000
Qty.1
Sub-Total
$52,000
Total Projected Cost for Generators:
$140,000
Projected Cost for Two (2) 6500 Gal. Water Trucks for Water Utilities
Tractor Trailer
Qty. 2
Sub-Total
$545,000
6500 Gallon Water Tanker
Qty. 2
Sub-Total
$140,000
Total Projected Cost for Water Trucks:
$372,940
Projected Cost for Three (3) Pneumatic Rollers for Road and Bridge