Discussion and possible action to approve the release of retainage in the amount of $3,243.75 to Porras-Nance Engineering, (Purchase Order 2019-00003179) for the GPS Utility Survey Engineering Services for the Water Distribution and Sewer Collection System Mapping for the Rio Bravo/El Cenizo Project; and authorize the County Judge to sign any relevant documents and any other matters incident thereto. [Funded under the 2016 Bond #7220-7270-001-432001 (Professional Services)]
Issue: Five Percent (5%) of the construction project amount is held in retainage from the contractor to ensure that any deficiencies which may arise are addressed by the contractor.
Solution: Approve and release retainage and close out project.