APPROVAL OF CHANGE ORDER NO. 1-8 FOR THE DETOXIFICATION FACILITY PROJECT
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve Change Orders No. 1-8 in the amount of approximately $330,000.00 to Quantcorp Construction for the Webb County Detoxification Facility with additional approval to transfer funds from Account 3907 Interest Income to 3902-7230-001-474501 (Construction in Progress); and authorize the County Judge to sign any relevant documents and any other matters incident thereto. [Fund #3907 (Interest Income) and Account #3902-7230-001-474501 (Construction in Progress)]
Issue: Webb County and the City of Laredo have additional items needed in order to finish this project:
001-Days, 002-Interior wall and framing, 004-Provide STC-50 Opening mark assembly, 005-Demolition of door frames / installation of refrigerant lines, 006-Interior cameras and electrical equipment. 007-Assessment of exterior walls, 008-Architect Fees.
Solution: Approval of new proposed changes.
Result: Approval of change orders will continue and finish with project modifications.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
Account #3907 (Interest Income) and Account #3902-7230-001-474501 (Construction in Progress)