Discussion and possible action to approve, by Order, the following budget amendment (line item transfer) for the Engineering Department:
Acct. Number
Acct. Name
Adopted
Request
Current
End Bal.
From:
3716-7230-709-470000
Mangana Hein Road-Capital Outlay
$64,995.04
$20,000.00
$64,995.04
$44,995.04
To:
3716-7230-709-432001
Mangana Hein Road-Professional Services
$20,879.00
$20,000.00
$20,879.00
$40,879.00
Issue: Vendor will provide professional services for as-built evaluation for drainage crossings A, B. and C of the Mangana Hein Road Project. Please refer to attachment for additional information. Time to complete: 45 days.
Solution: Approval of line item transfer.
Result: Funding will allow continuation of services for this project.