Discussion and possible action to approve Change Order #1 to the J-Starr Construction Inc., Golf Club Kitchen Renovation Contract in the amount of $18,517.00 and the addition of 15 days. This is to cover additional work required due to badly weathered roof supports, building leaks and additional paint prep and paint work. The new contract amount will be $157,583.24. [Account #746-6001-8601 (Bond Series 2013)]
Background:
Contract has a credit of $480.00 on flooring modifications made, which was used to reduce Change Order #1.
Previous Court Action:
On August 11, 2014 Commissioner Court approved Agenda Item #19, Remodel/Construction contract in the amount of $139,066.24 to J-Starr Construction, Inc. for the Golf Club Kitchen Renovations.