Discussion and possible action to authorize Webb County Economic Development Department to submit to Texas Department of Agriculture (TDA) Change Order No. 1 to the A Plus Plumbing Contractor contract for a decrease amount of Five Hundred Forty-Eight Dollars and No Cents ($548.00) for the Colonia Pueblo Nuevo House-to-Line Water & Sewer Connection Project TCDP #713015 and authorize the County Judge to sign all relevant documentation. This will not impact the general fund.
Issue: At the time of solicitation, contractor projected a contract amount but when actual work was performed, the actual contract amount was determined after completing the homes.
Solution: The change will adjust the construction contract and will be submitted to Texas Department of Agriculture (TDA) for review and approval.
Result: Construction Project of water & sewer connections in Colonia Pueblo Nuevo will be completed and closed out.