SUPPLEMENTAL WORK AUTHORIZATION NO. 8 TO WORK AUTHORIZATION NO. 1
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering
Subject:
Discussion and possible action to approve Dannenbaum Engineering Corporation's Supplemental Agreement No. 6 to Main Contract and Supplemental Agreement No. 8 to Work Authorization No. 1 for the International Blvd. set of Plans of the Loop 20/International Blvd Project Project (CSJ 0086-14-051) to reflect the changes to the Texas Department of Transportation (TxDOT) pavement design and upgrade from the 2004 to 2014 TxDOT Specifications Book. These additions in scope of work will have a net change effect of $56,541.06 for a maximum amount payable of $3,363,724.30 of which 100% will be reimbursed by the Texas Department of Transportation (TxDOT), subject to their approval; and authorize the County Judge to sign all relevant documents. [Account #737-8001-6022 (Professional Services)]
Issue: TxDOT's pavement design was changed for the International Blvd Set of Plans and specifications must meet the new TxDOT 201 Specifications Book.
Solution: Add scope of work activities to include the changes to TxDOT's pavement design and meet the new TxDOT 2014 Specifications Book requirements.
Result: Include changes that are required and approved by TxDOT to the pavement design of the International Blvd and reflect specification of the new 2014 Specifications Book.