Discussion and possible action to approve and allow the Engineering Department to re-task some of the savings funds ($54,185.93) to redo the stucco work on the exterior walls of the Community Supervision & Corrections Department/Police Athletic League (C.S.C.D./PAL) building renovations on Hwy 83S in the amount of $26,000.00, this will cover all materials and labor. [Account #742-8001-8801-12 (Rebuild Restitution Center Series 2013)]
Issue: The building's exterior stucco on three walls is not included in the Contractor's price.
Solution: Funding from price reduction can be utilized to refinish old exterior walls at no additional cost to this project.
Result: Exterior walls can be done to improve the exterior look of the existing building at no additional cost to theproject.