Discussion and possible action to authorize Change Order #2 in the amount of $19,573.65 for the New Fire Station and Administration Building to Hydroworks, Inc. [Accounts #3195-3140-001-470000-125 and #3195-20600]
Issue: Change Order #2: Relocation of Meter Loop as per A.E.P.-$7,000.00, Main sign extra cost-$4,769.65 (over project allowance of $3,500.00), Install interceptor for rain run-off from Life Downs (labor only-$9,200.00, less credit on plaque-$1,396.00. Total Change Order amount $19,573.65.
Solution: Increase contract by $19,573.65.
Result: All corrective actions and shortages resolved.
Background:
Purchase Order #16-0004722
Previous Court Action:
N/A
Fiscal Impact
Budget Account Number:
0
Funding Source:
0
Balance:
0
Financial Impact:
[Account #3195-3140-001-470000-125 and #3195-20600]