Discussion and possible action to approve the following budget amendment (line item transfer) within the Water Utilities fund:
Acct. Number
Acct. Name
Amount
Bal.
End Bal.
From:
7220-7280-001-474501
Construction in Progress
$25,000
$1,588,885
$1,563,885
To:
7220-7280-001-432001
Professional Services
$25,000
$21,140
$46,140
Issue: Insufficient funds in existing professional services account for funding of Engineering Contract for improving the El Cenizo Water Distribution System in conjunction with the Elevated Storage tank TCEQ requirements.
Solution: Approval of Transfer Request
Result: Allocation of Purchase Order to Engineer to commence project.